American Association of State Highway and Transportation Officials

Special Committee on Research and Innovation

 

FY2023 NCHRP – IMPLEMENTING UTILITY INVESTIGATIONS

 

Problem Number:  2023-D-08

 

Problem Title

Guidance for Implementing Utility Investigations in Alignment with Project Delivery

 

Background Information and Need For Research

While it is recognized to be in the public interest to permit the installation of utility infrastructure in roadway right-of-way (ROW), the practice has contributed to utility-related issues being one of the leading causes of delays for transportation projects (FHWA, 2018). These delays are often attributed to unknown or inaccurate utility locations. Utility investigations, inclusive of subsurface utility engineering (SUE), are procedures state departments of transportation (DOTs) can implement to locate utilities and assist their project development teams with avoiding these issues. However, there is little guidance specific to an alignment of the timelines for implementing utility investigation procedures with those of the project delivery process. Further, there are many factors that influence the optimal approach of utility investigations for a specific project, such as project type, project environment, utility types, etc. Further, there are variations in utility investigation needs based on the timing of design elements within the project delivery process, e.g. what utilities investigations are needed for alignment and grade design, and when will that design occur.

 

SUE is a standardized process defined by the American Society of Civil Engineers (ASCE) 38-02 “Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data.” SUE has been presented as a useful tool for utility investigations but varies in application and understanding. Some state DOTs have been successful in SUE practices while others are still in the development of their program. Improved understanding could lead to more widespread utilization or a change in protocol for many state DOTs. There is a gap in guidance for the implementation of SUE, quality assurance for SUE deliverables, and depiction guidelines at state DOTs. While the American Society of Civil Engineering (ASCE) 38-02 standard is effective in defining the process, there is still a need for a guide for SUE implementation to help state DOTs in development of a SUE program. Recent updates to ASCE 38-02 will include guidance for depiction and present that standard as a more holistic utility investigation approach.

 

It should be clearly noted that best practice does not necessarily involve a linear application of SUE quality levels to the phases of project development. That is, it is not necessary to perform SUE quality level D, followed by C, and so on. A more appropriate practice would be the identification of quality level needs according to project characteristics, where multiple SUE quality levels would be collected concurrently but may vary by location and project need.

 

The needed guidance for implementing utility investigation approaches therefore includes:

•           Application criteria;

•           Depiction approaches;

•           Prequalification of service providers;

•           Deliverable expectations;

•           Quality assurance practices;

•           Alignment of utility investigation to design phases;

•           Alignment of design element timelines to utility investigation; and

•           Approaches to staffing and roles, and other programmatic decisions.

 

Literature Search Summary

ASCE 38-02

23 CFR 645 Subpart A and B

 

Research Objective

The primary objective of this research is to develop guidance for DOTs to strategically align utility investigations to project development phases. The guidance to be developed will address:

 

The strategic implementation of SUE/ utility investigations by

•           Project Type

•           Project phase and delivery step/scope and need

•           Design element timelines and needs

•           Project environment (rural/urban)

•           Documented geophysical site conditions and equipment selection, including the use of advanced equipment, such as multichannel ground penetrating radar

•           Facility Types and densities

•           Public interest and project risk

•           Project delays

Communicating and modeling the utility investigation information should also be addressed in this guidance for:

 

•           Depiction approaches, showing quality levels on plans

•           3D modeling and clash detection, to include buffers and all ranges of conflicts (direct, indirect, etc.)

•           Risk assessment of 3D subsurface utility models

•           Use of information for design/project development (e.g. schedule changes) decision making

•           Maintenance of utility investigation data through the design process

•           Communicating as-built/relocated utility information

•           Quality assurance of information collected.

 

The research objective will be achieved through the completion of research tasks to be described by the research team that best addresses the research questions and goals. Possible tasks include:

 

•           State department of transportation surveys

•           Survey of consultant design firms

•           Examination of case studies and best practices, e.g. SHRP2 products R01A, R15B and ASCE 38 Guidelines

•           Development of guidance documents

•           Conduct an exploratory workshop for refinement

•           Implement a proof-of-concept trial on a state DOT project

•           Production of final guidance.

 

Urgency and Potential Benefits

Inappropriate utility investigations contribute to the $50 billion drain on the United States economy cause by utility and highway coordination. This is also a major factor in utility impacts being one of the top three causes of delays for projects. The proper investigation of utility locations will help project teams eliminate substantial risk from DOT projects. DOTs are highlighting the importance of utility investigation and coordination just as more utilities are being installed within ROW.

 

Implementation Considerations

Standards are needed before these trends exacerbate the previous defined problems.   

 

Recommended Research Funding and Research Period

The estimated cost is $400,000 and duration is 36 months.

 

Problem Statement Author(s): For each author, provide their name, affiliation, email address and phone.

Written – 09/2021–Roy Sturgill, Gary Young, Deanne Popp, Corey Biddle, Lance Parve

 

Potential Panel Members: For each panel member, provide their name, affiliation, email address and phone.

AASHTO Utility Project Scoping & Coordination Technical Council Chair

AASHTO Committee of Right of Way, Utilities and Outdoor Advertising

Utilities Subcommittee

Patrick Overton

Florida Department of Transportation

State Utility Engineer

605 Suwannee Street, MS 75

Tallahassee, Florida 32399

Office# (850) 414-4379

patrick.overton@dot.state.fl.us

 

Person Submitting The Problem Statement: Name, affiliation, email address and phone.

Patrick Overton

FDOT State Utility Engineer and Vice Chair for Utility Scoping, Coordination, and SUE TC

Patrick.overton@dot.state.fl.us

(850) 414-4379