American
Association of State Highway and Transportation Officials
Special
Committee on Research and Innovation
FY2023
NCHRP PROBLEM STATEMENT TEMPLATE
Problem Number:
2023-D-02
Problem Title
Guidebook
on Progressive Design-Build for Transportation Projects: Project Planning
through Project Implementation
Background Information and Need For Research
Transportation
agencies started using design-build (DB) over 25 years ago, and it is now
considered a standard “tool in the toolbox.” The most commonly used methodology
for DB contractor selection involves a best value process, with significant
weight accorded to price, resulting in a fixed price contract for design
development and construction. Progressive Design-Build (PDB) is an advancement
of fixed price DB that allows early contractor involvement, including elements
similar to construction manager/general contractor (CM/GC). It transfers design
and construction responsibilities to a design-build team starting with a
preliminary planning and design phase through construction completion, with
negotiation of the price for final design and construction at the end of
preliminary design phase, similar to the process used for CM/GC pricing. The
qualifications and experience of the DB team are significant factors in
contractor selection, and while legislation often dictates consideration of
price in the selection, in some cases public owners use a pure
qualifications-based selection process.
PDB
contracts include procedures for development of the design, schedule/phasing
plan and a price for final design and construction which typically is in the
form of a Guaranteed Maximum Price for Construction (GMP). The development of
the GMP is a key component of PDB as it allows owners to hire a
designer-builder without a price commitment for final design and construction
until after reasonable design details are defined. In addition, to ensure
agencies are able to make the price reasonableness determination required for
federally funded projects, the public owner often hires an Independent Cost
Estimator (ICE) to develop a full price of construction based upon an agreed
upon scope of work and schedule. The negotiated price typically includes
allowances and contingencies to account for potential unknowns and risks that
are agreed upon by the owner and the contractor. Several state departments of
transportation (DOTs) have started to use PDB, based on models that have been
successfully used in water/wastewater, airport, municipal street/roadway
projects, flood control, and transit sectors.
The
documented benefits of using PDB include:
• greater agency control of design
decisions, scope, cost, and schedule;
• flexibility of delivery;
• risk mitigation and contingencies;
• innovative project-specific solutions
and better scoping of owner needs and expected outcomes;
• accelerated schedule and phasing
opportunities;
• increased diversity in contracting
opportunities and workforce development;
• increased life-cycle value for money;
• and greater designer and contractor
collaboration.
Moreover,
in contrast to traditional design-bid-build (DBB) and CM/GC, and like fixed
price DB, PDB transfers design liability to the contractor.
Only a
few states have implemented PDB to date. For example, Maryland successfully
used PDB for their I-270 project and Utah used PDB for their US 89 project.
Washington began their first PDB on a grouping of fish passage projects.
California, Missouri, Michigan and Florida also are interested in PDB to
maximize the dual benefits of DB and CM/GC delivery methods. However, little
PDB guidance is available, if any, for state DOTs to implement PDB on their
highway projects.
Literature Search Summary
PDB is a
project delivery method that is of great interest to many sectors and more
specifically to the transportation sector, that has not been the subject of
specific research. There has been a few CRP publications (TCRP G-08, A
Guidebook for the Evaluation of Transit Project Delivery Methods and ACRP
A01-05, A Guidebook for Airport Capital Project Delivery Systems, ACRP Legal
Digest 38: Legal Issues Related to Large-Scale Airport Construction Projects)
addressing various aspects of PDB whether in terms of selection or legislation
requirements. However, to date no detailed guidance has been developed for DOTs
to implement it most effectively and accrue many of the pronounced advantages.
Specifically, no prior research has been conducted for NCHRP on PDB. At the
state DOT level, Alleman and Tran (2021) studied Maryland’s I-270 PDB project
and the challenges of implementing PDB in highway construction. However, in
most these studies, the thrust of the research was to assist transit and
airport agencies in making their project delivery selection decision and
included very little detail on the mechanics and implementation best practices
of PDB.
NCHRP
10-85: A Guidebook for Construction Manager-at-Risk Contracting for Highway
Projects (published as the AASHTO CMGC Guide) is related to this research
project in that CM/GC uses a negotiated pricing structure similar to that used
in PDB. This research would provide guidance that is also relevant to the DB
contractual environment. ACRP Legal Digest 38: Legal Issues Related to
Large-Scale Airport Construction Projects address the legal framework upon
which PDB could be implemented effectively within the regulatory constraints.
Research Objective
Because
of the benefits offered by PDB, combined with the growing reluctance of the
contracting community to bid on fixed price DB contracts due to the risk of
cost overruns, there is a need to investigate how PDB can be most effectively
implemented on highway projects. This will require research into key issues
such as statutory authority and permits needed for PDB, availability of and
effects on the owner’s in-house staff, level of design detail and control, and
level of risks, among others. The main objective of the proposed research is to
develop guidelines that will assist state DOTs in the effective and efficient
use of PDB for highway projects. The research will answer the following
questions:
1. What is the current state-of-practice
for successful implementation of PDB? How could the current state-of-practice
and lessons learned of PDB from other sectors’ projects apply to highway
projects? What are the benefits and challenges of PDB beyond fixed price DB,
specific to highway projects?
2. What are the critical skill sets,
knowledge, resources, legislation, etc., that agencies need prior to executing
PDB projects? How do traditional agency functions and responsibilities change
under PDB? How do these changes impact
staff requirements and roles? How does an agency representative become a champion
for PDB? What type of training is needed to implement PDB?
3. To maximize the likelihood of selecting
the best PDB contractor for a specific project, what evaluation elements should
be emphasized when developing and implementing a PDB procurement? These
elements include team qualifications and availability, selection criteria, and
procurement processes, among others.
4. What are the skill sets, knowledge,
team structure and experience (i.e. qualifications) expected of a contractor
team (builder and designer) to successfully deliver a PDB project?
5. What are the challenges in
administering a PDB contract and how can they be overcome?
6. What are the inherent conflicts between
PDB delivery and NEPA (National Environmental Policy Act) requirements? How can
they be addressed?
7. What are the funding restrictions from
a timing and scoping perspective?
8. What other barriers exist to utilizing
a PDB delivery method?
How are
risks allocated and effectively managed on PDB projects? How should contractual
“off-ramps” be structured to ensure that the owner has appropriate alternatives
if issues arise during the preliminary design phase or pricing is too high?
What are the risks and benefits of exercising an “off-ramp,” including the
timing of “off-ramp” and professional liability? How can the risks be
mitigated?
Urgency and Potential Benefits
This
research would result in an NCHRP research report providing updated information
about successful practices, case law and statutes relating to PDB project
delivery to assist agencies in evaluating when PDB should be considered for a
project, and how to develop the framework for successful use of PDB. If added
to the DOT project delivery standard “toolbox,” PDB also represents a possible
solution to reducing the costs of unrealized risks found in fixed price DB
projects, and increases the pool of contractors interested in proposing on DB
projects, by permitting a negotiated construction cost based on more design
detail with public owner control of the design decisions.
Implementation Considerations
This
research will be utilized by Planners, Engineers, and Contractors involved in
highway construction planning, scoping, development, construction, and
maintenance activities. This guidebook
share lessons learned from agencies that have already utilized PDB, and will
identify all of the necessary tools to guide an agency from the planning phase
to implementation phase.
Recommended Research Funding And Research
Period
$300,000
for 24 months.
Problem Statement Author(S): For each author,
provide their name, affiliation, email address and phone.
• Eric Kahlig, PE, Ohio Department of
Transportation – eric.kahlig@dot.ohio.gov; 614-387-2406
• Douglas Gransberg, Ph.D. Chair AFH 15 – dgransberg@gransberg.com;
405-503-3393
Potential Panel Members: For each panel
member, provide their name, affiliation, email address and phone.
• Eric Kahlig, PE, Ohio Department of
Transportation – eric.kahlig@dot.ohio.gov; 614-387-2406
• Ryan Mitchell, Michigan Department of
Transportation – mitchellr13@michigan.gov 517-614-7025
Person Submitting The Problem Statement: Name, affiliation,
email address and phone.
Jason
Humphrey, P.E. South Dakota Department of Transportation; AASHTO COC Research
Chair; Jason.humphrey@state.sd.us; 605-773-4391